Hi use following technique for time estimation of project.
P.E.R.T
Programm evaluation and review technique.
It averages Pessmistic estimation,Most Likely and Optimistic.
A.E.T.=Aprox.Estimated time
P.E.=Pessimistic Estimation
M.L.E.=Most likely Estimation
O.E.=Optimistic Estimatoin
A.E.T.=(P.E+4(MLE)+O.E)/6.